Allocate serialized material to a job without a serial number

Inventory Edition Only

Background

Once you get comfortable ordering/receiving and assigning serial numbers to jobs, you might find it useful to assign a quantity of needed material to a job before you assign serial numbers. This is an advanced approach, so get comfortable with the basics first (see related articles at the bottom of this page).

This approach is particularly useful when you are  special ordering material for a customer.

Step-by-Step

To add an unserialized quantity of material to a job without serial numbers, simply find the desired product variant and enter the needed amount without assigning serial numbers. It's typically adequate to estimate 50 sq ft per slab.

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.